When I select a project in a Request for Change in Solution Manager 7.1 SP7, I cannot select (nor does it autopopulate) with the production ibase from the logical component that is associated with the project. If no project is selected, then all ibases are selectable. I would like to select both the project and the production ibase for the Request for Change however though. Any ideas on what might be the problem?
Details:
Landscape is DEV -> QA1 -> QA2 -> PROD
QA2 and PROD are virtual systems in TMS
All systems have been setup in the LMDB and ibases have been generated successfully
Logical component for the SolMan project has been setup where DEV is in System Role "Development", QA1 is in system role "Quality Assurance", QA2 is in system role "QA Final" (user defined system role), and PROD is in system role "Production".
Charm is active and task list has been generated to include DEV, QA1, QA2, PROD and QA2 and PROD are showing as virtuals in the task list as well.